Fuxin municipal solid waste landfill leachate treatment service procurement project
Construction time: March 2020
Capacity and process: 1000t/d, pretreatment + two-stage DTRO (90bar) + MVR evaporation
Tail water discharge standard: Table 2 in Liaoning Local Sewage Discharge Standard (DB21627-2008)
Project features: This project is a large-scale and full-capacity project for emergency disposal operations. Equipment was required for arrival and installation within 10 days and for debugging and operation (namely discharging tail water) within 20 days, which were high requirements on the stability and reliability of the equipment and operation management.